Schedule for EAS Required Monthly Tests
The Required Monthly Test
(RMT) will occur on the First Wednesday of the month.
Wisconsin stations should
receive an RMT from their regional NOAA weather station on odd months at approximately 8:50am.
On even months stations should receive an RMT from WPR's Radio Operations Center in
Madison through the State Relay stations at approximately 11:50pm.
If an RMT is carried by the Wisconsin Public Radio
stations, they will normally NOT carry a Weekly Test since only one test
per week is required. If for some reason a Required Weekly Test is
missed or impaired, it will be "made up" on the Friday of that week at
the same scheduled time of day.
View a summary of the New
EAS Codes from Gary Timm released on 09/11/04.
If you have questions on this or other EAS issues, contact the EAS
coordinators in your operational area. The East Central area is handled by Steve
Brown (920-831-5659) and Steve Konopka (920-465-2675).
The Wisconsin Plan can be found at the website for SBE Chapter 24 (Madison,
Wisconsin): http://www.sbe24.org/eas/ |